A group of 69 former bureaucrats has asked the Union environment ministry to scrap the proposed 1,750 MW Demwe Lower Hydroelectric Project on the Lohit River in Arunachal Pradesh, citing ecological concerns. In a letter dated November 23, also addressed to Chief Minister Pema Khandu and the Standing Committee of the National Board for Wildlife (SC-NBWL), the signatories questioned repeated attempts by successive governments to push the project despite scientific objections, legal interventions and local opposition. The signatories include former Delhi lieutenant governor Najeeb Jung and former Kerala principal chief conservator of forests Prakriti Srivastava. No response was immediately available from the Union environment ministry or the Arunachal administration.
According to the letter, the project would require diversion of 1,416 hectares of forest land, submerge nearly 1,590 hectares and involve felling of around 43,000 trees in an ecologically sensitive evergreen rainforest. The former officials said opposition dates back to 2010, when the project received initial environmental clearance, prompting Mishmi and other indigenous communities, environmental groups and civil society organisations to mobilise against the dam to protect the sacred Parashuram Kund and downstream ecosystems. They warned it could threaten the critically endangered white-bellied heron and fragment tiger habitats and wildlife connectivity across the larger landscape, including Kamlang, Namdapha and the proposed Dibang Tiger Reserve.
The letter also raised questions over the project's regulatory history. It said all non-official expert members of the SC-NBWL opposed the proposal in October 2011, but the then Union environment minister granted wildlife clearance in 2012, overriding their objections. The National Green Tribunal suspended the approvals in 2017 and directed a fresh examination, including cumulative downstream impacts. The former bureaucrats alleged that a reconstituted committee cleared the project in 2018 without the comprehensive multi-seasonal assessment sought by the tribunal, relying instead on what they described as a flawed Wildlife Institute of India study. The project remained stalled owing to financial difficulties faced by its developer, among other factors, before being acquired by the Greenko Group in 2026.
The signatories questioned the latest regulatory exercise, saying the SC-NBWL, reconstituted in March 2026 with only two independent experts, considered the proposal in July primarily to approve the change of developer from Athena to Greenko, and allegedly failed to conduct a fresh wildlife assessment as directed by the NGT. They also challenged the argument that large dams in Arunachal Pradesh could help India establish prior appropriation rights over river waters and counter China's upstream hydropower activities in the Brahmaputra basin, arguing that without a bilateral water-sharing treaty, downstream infrastructure would not prevent China from diverting water upstream. They urged authorities to reconsider the project's viability in light of its ecological, social and legal implications.